Large Research University

Opportunity: Design, build and install a central hydraulic system in a state-of-the-art testing facility.

Result: RG Group built the massive 375 hp, 500 gallon hydraulic power unit and installed in excess of 2500 feet of stainless steel pipe and tube in support of this state-of-the-art facility. Construction of the power unit began in our facility in York, PA in September of 2010. The entire piping system was designed, fabricated and laid out in our York facility prior to site work beginning in April 2011. Installation, commissioning and successful turnover of the system was complete by July 2011.

The RG Advantage: The engineering firm with primary responsibility to deliver the facility received regular schedule and cost updates, anticipated progress billings, and an effortless transition after commissioning. A comprehensive package of technical information accompanied the system to include: Operation and Maintenance manuals, as-built drawings, schematics and component data sheets.

You can count on RG Group for excellent quality and service

Contact us today